Applicability & Payment

Impact Fees
Applicability and payment of road impact fees will be assessed at the time of platting and paid at the time of each building permit application submission (see grandfathering below).

The following determines if impact fees are applicable to a plat:
  • For plats approved by Planning and Zoning prior to April 1, 2007 and may or may not be recorded: No impact fee required for all building permits applications before April 1, 2008
  • For plats approved by Planning and Zoning after April 1, 2007: Impact fee required. Use the schedule of fees and fee calculation worksheet to determine proper fees
  • For building permits applied for after April 1, 2007 Impact fee required. Use the schedule of fees and fee calculation worksheet to determine proper fees In order to minimize delays in processing, it is recommended that the required fees be determined as completely as possible before application for a building permit, using appropriate form.